Sludge was stored in barrels for treatment and disposal.As a 1st step, the sludge was transferred to the earthen lined pit
for Bio remediation. The client wanted the treatment of the sludge to be done inside the pit.
The total percentage of hydrocarbons in this sludge was recorded as 11%. The objective was to bring it down upto 2%. We
have conducted all necessary treatments in the sludge pit as per schedules.
Sludge converted to rich manure
sludge before treatment
Result
This sludge has been successfully remediated in the site within 6 months.
Achievement:
The total percentage of hydro-carbons was brought down to less than 2%.